Quantcast
Channel: Hong Kong Land Law Blog
Viewing all articles
Browse latest Browse all 481

Contractual obligation to produce an architect’s certificate before completion: an implied term that it will be produced within a reasonable time before completion

$
0
0

In Guo Jianjun v Dragon Fame Investment Ltd ([2015] HKEC 1986, CA) S entered into an agreement to sell to P four office units (all on the same floor of the building). The agreement contemplated that there would be a re-partitioning of the office units owned by S. The units to be sold were the units as they would be after the re-partitioning. The contract contained a clause obliging S to obtain the certificate of an ‘Authorized Person’ to confirm the legality of the re-partitioning works. The agreement went on to provide that P would not raise any requisitions, queries or objections concerning the re-partitioning works. The re-partitioning works were carried out soon after the agreement was entered into. S produced an architect’s certificate of compliance. This satisfied S’s contractual obligations but it was produced at 6.07 pm on the completion date. It was common ground that the midnight rule applied. P argued that S was in breach of an implied obligation to produce the certificate at a reasonable time. It rescinded and sought the return of the deposit and damages. S argued that there was no implied term and that it was enough for it to have produced the certificate before midnight on the completion date.

The Court of Appeal (Lam V-P giving the judgment) looked at the English and Hong Kong authorities setting out the modern approach to contractual interpretation. This required the court to look at the rest of the contract and the whole of the relevant context / factual matrix. It also looked at what was said in Belize Telecom concerning the implication of terms (and linking this process to the broader process of contractual interpretation).

The obligation had to be construed in the context of the related clause which barred the raising of requisitions concerning the partitioning. It was also necessary to take account of the obvious commercial purpose served by the obligation: if S did not produce an adequate certificate there could be a doubt as to the legality of the works which could prevent P from giving good title on any future sale. Thus, there was to be implied a term ‘that the certificate would be a proper certificate prepared by an authorized person in good faith’ ([34]).

Given that the architect was commissioned by, and would report to, S P had to be given a reasonable time to assess whether or not the certificate satisfied the contractual obligation. They had to be given a reasonable time in which to do so. A term to this effect was to be implied ([41]).

What was a reasonable time? Had the implied obligation been observed in this case? The court referred to its earlier decision in Summit Link v Sunlink Group:

‘What should be considered as a reasonable time must be considered in the light of the prevailing circumstances, including the parties’ knowledge at the time if it can be proved and what the parties would each be reasonably contemplating at the time.’ (at 735 – 6 per Woo JA).

The court also referred to the headnote to the report of Kensland Realty Ltd v Whale View Investment Ltd ((2001) 4 HKCFAR 381):

‘The time which a vendor must allow, was the time reasonably required by the purchaser to perform its obligations, in relation to completion, in the ordinary course of business. This would include the purchaser’s dealing with bankers and solicitors.’

Lam V-P explained what this meant in the present case:

‘I am therefore of the view that the certificate should have been provided to the plaintiffs’ solicitors within a reasonable time before the end of the office hours [on the completion date]. The reasonable time should be long enough to afford the plaintiff’s solicitors a reasonable opportunity to conduct the checks which are reasonably necessary and to do so in the normal course of business. The time should not be so short that the solicitors would have to stretch all their available resources to the extreme so as to accomplish the tasks.’ ([46]).

Further, ‘one should proceed on the general assumption that purchasers will rely on mortgage financing in a conveyancing transaction’ ([50]).

Production of the certificate after the close of business on the date of completion did not satisfy the reasonable time requirement.

Michael Lower

 

 

 



Viewing all articles
Browse latest Browse all 481

Trending Articles